CORPUS CHRISTI, TX – Street closures along the City’s major streets impacting motorists and pedestrians are listed below. These closures may be due to construction, special event activity, or maintenance. All closures are subject to change due to weather, emergency work, or other circumstances.
Work zone safety is a priority. Motorists are advised to slow down, follow posted speed limits, pay attention, watch out for workers, obey signs and flaggers and allow additional travel time for delays.
CITY STREET RECONSTRUCTION OR MAINTENANCE PROJECTS
Ayers Street Pedestrian Improvement and Turn Lane – South Padre Island Drive (SPID) to Gollihar Road (Bond 2014)
During this phase, the following traffic changes and lane closures are implemented:
- Northbound Ayers Street is closed at the Crosstown/SPID Interchange (frontage road) intersection. Thru traffic is encouraged to seek alternate routes to access businesses in the area.
- Ayers Street is also reduced to one lane, one-way traffic from Gollihar Road to SPID (southbound direction only).
- Johanna Street to Crosstown/SPID Interchange (Northbound) – The outside thru lane on Ayers Street is closed approaching the Crosstown/SPID interchange. This lane closure will continue through the underpass of SPID. This closure will not impact access to the eastbound frontage road of SPID.
- Johanna Street to Crosstown/SPID Interchange (Southbound) - The left-turn lane and median openings are closed.
- Crosstown/SPID Interchange & Ayers Street Intersection (Northbound) – Northbound Ayers Street is CLOSED at the Crosstown/SPID Interchange intersection. Motorists must use alternate detour routes such as the SH 286 northbound frontage road, Gollihar Road, Kostoryz Road, or McArdle Road to access local businesses.
- Crosstown/SPID Interchange to Gollihar Road – Ayers Street is reduced to one lane, one-way traffic flow in the southbound direction only. Access to all local businesses is provided.
- Ayers Street and Gollihar Road Intersection – The outside thru lane on Ayers Street, in the southbound direction only, is closed approaching the Gollihar Road intersection.
- SH 358 Frontage Road (Eastbound) – The shared thru left-turn lane is closed.
RTA bus stops are closed from Gollihar Road to SPID. Bus stops remain open at the Port Ayers Transfer Station.
Brawner Parkway– Kostoryz Road to Carroll Lane (Bond 2018)
During Phase 1A of construction, Brawner Parkway (south of median) in the eastbound lane. The westbound lane will remain open for use during this first phase of construction.
Delgado Street – Salazar Street to Dead End (Residential Street Rebuild Program)
Delgado Street, between Salazar Street and the Dead End, is closed for reconstruction. The contractor will provide local access only to residents along Delgado Street.
Denver Avenue – Doddridge Street to Jackson Place (Residential Street Rebuild Program)
Denver Avenue, between Doddridge Street and Jackson Place, is closed for reconstruction. The contractor will provide local access only to residents along Denver Avenue.
Holly Road – Crosstown Expressway (SH 286) to Greenwood Drive (Bond 2012)
Two-way traffic has been restored on Holly Road. Daily Lane closures will be required as construction nears completion.
Laguna Shores Road – South Padre Island Drive to Graham Road (Bond 2018)
Laguna Shores Road, between South Padre Island Drive and Graham Road, is closed for reconstruction. Motorists are advised to use Waldron Road as an alternative route for thru traffic. Access is provided within the closed roadway segments to residences and businesses within the work zone.
Laguna Shores Road – Hustlin’ Hornet Drive to Caribbean Drive (Bond 2018)
Laguna Shores Road, between Hustlin’ Hornet Drive to Caribbean Drive, is closed for reconstruction. Motorists are advised to use Waldron Road as an alternative route for thru traffic. Access is provided within the closed roadway segments to residences and businesses within the work zone. The following short-term closures are in place so the Contractor can perform utility work:
- There is a short-term closure of Laguna Shores Road south of Beasley Road to perform utility work and stormwater installations.
Laguna Shores Road – Mediterranean Drive to Wyndale Street (Bond 2018)
Laguna Shores Road, between Mediterranean Drive to Wyndale Street, is closed for reconstruction. Motorists are advised to use Waldron Road as an alternative route for thru traffic. Access is provided within the closed roadway segments to residences and businesses within the work zone.
Leopard Street – Palm Drive to Nueces Bay Boulevard (Bond 2018)
Travel lanes are reduced to one lane, in each direction, along the westbound lanes (north side) of Leopard Street between Nueces Bay Boulevard and Battlin’ Buc Boulevard. The southern part of the Leopard Street and Nueces Bay Boulevard intersection remains closed. Nueces Bay Boulevard is also closed to thru traffic between Leopard Street and Up River Road.
Ocean Drive Rehabilitation Project – Airline Road to Louisiana Avenue
Ocean Drive is reduced to one lane, in each direction, on the east side of Ocean Drive (northbound lanes) between Airline Road and Louisiana Avenue. Access to properties within the work zone will be maintained at all times.
Park Road 22 Bridge and Channel – Whitecap Boulevard to Commodores Drive (SH 361)
Phase 1 of the Park Road 22 Bridge and Channel project is underway on the east side (northbound lanes) of Park Road 22. Motorists traveling northbound along Park Road 22 are shifted to the southbound lanes (west side) between Cruiser Street and Compass Street. Travel lanes are reduced to one lane, in each direction, along the southbound lanes (west side) between Cruiser Street and Compass Street.
Staples Street – Baldwin Boulevard to Kostoryz Road (Bond 2018)
During Phase 1 of construction on Staples Street, between Baldwin Boulevard and Kostoryz Road, drivers and pedestrians should expect the following traffic changes:
- The northbound lanes and center turn lane (east side) of Staples Street, between Baldwin Boulevard and Kostoryz Road, will be closed for construction. Traffic will be shifted to the west side of Staples Street (southbound lanes) and reduced to one lane in each direction.
- Traffic along northbound Staples Street will be shifted to the west side (southbound lanes) of the roadway approaching the Kostoryz Road intersection.
- The inside left-turn lane will be closed along Kostoryz Road at the Staples Street intersection.
- The intersection of Louisiana Avenue and Kosar Street with Staples Street, on the east side, is closed to install storm water utilities.
- Sidewalks will be closed on the east side of Staples Street, within the construction zone.
Swantner Drive – Indiana Avenue to Texan Trail (Bond 2018)
Swantner Drive is closed to thru traffic between Indiana Avenue and Ralston Avenue and also between Texan Trail and Glazebrook Street for reconstruction. Chamberlain Drive is also closed between Reid Drive and Swantner Drive. Access to local residents is provided.
CITY PERMITTED CLOSURES
7th Street – Morgan Avenue to Elizabeth Street, Wastewater IDIQ (IPR South Central LLC)
Contractors for the city will temporarily close 7th Street between Morgan Avenue and Elizabeth Street to perform repairs to a sanitary wastewater manhole and lateral lines. Additional temporary intersection closures at 7th Street and Elizabeth Street are required for pipe bursting operations and manhole rehabilitation. Local residential access will be maintained throughout construction. Temporary street closures are expected to last one month.
Brownlee Boulevard – Mary Street to Hancock Avenue, Wastewater IDIQ (IPR South Central LLC)
The contractor for the City has temporarily closed Brownlee Street to perform repairs to a sanitary sewer manhole and lateral lines. Additional temporary street closures along Morris Street between 14th Street and 11th Street are required to facilitate a temporary bypass sanitary sewer. Temporary street closures are expected to last several weeks.
Buffalo Street – Buddy Lawrence Drive to IH 37 Frontage Road
A private contractor is implementing daily flagger operation traffic controls to install new water and sewer service lines. Flagging operations are expected to last two weeks.
Compton Road – Central Street and 1St National Drive (IPR South Central LLC)
Beginning Monday, December 13, 2021, contractors for the City’s Utility Department will implement a one-day temporary full street closure on Compton Road to bury a bypass line underneath the street. The temporary street closure will be implemented two more times throughout construction to remove the bypass and for pavement repairs. Utility project in the area is expected to last 30 days.
Leopard Street – Tuloso Road to Clarkwood Road (STX Process Equipment LLC)
Beginning Wednesday, December 15, 2021, contractors for a petroleum pipeline will begin implementing daily closures in the westbound direction of Leopard Street between Tuloso Road and Clarkwood road. Lane closures are needed to provide a safe work area for the contractors performing maintenance to the pipeline. Temporary closures are expected to last 30 days.
McArdle Road – Ennis Joslin Road to Nile Drive (AEP Texas)
Contractors for AEP Texas are implementing daily, closures, and traffic shifts into the center turn lane, along westbound McArdle Road between Ennis Joslin Road and Nile Drive. Lane closures are being implemented to install new power poles and electrical cables along the north side of McArdle Road. This work is expected to last several weeks.
McBride Lane – Agnes Street to Steel Street (The Brandt Companies)
Beginning Monday, December 13, 2021, contractors for private commercial distributors will be implementing temporary flagger-controlled lane closures, to establish a safe work area for a crane lift. Temporary closures are expected to last one day.
Morris Street – 12th Street to 10th Street
Beginning Monday, December 13, 2021, contractors for the City’s Utility Department will implement temporary full street closure on Morris Street between 12th Street and 10th Street make wastewater line utility repairs. Intersection closure at 11th Street and 10th Street will also affect traffic. The temporary street closures will allow for a safe work area to excavate the street and perform necessary repairs. Street closures are expected to last 30 days.
Schatzell Street – North Chaparral Street to Water Street (Spectrum)
A Spectrum Contractor is performing utility installations along Schatzell Street, between North Chaparral Street and Water Street. Utility installations will also be performed along Water Street near the Schatzell Street intersection. This work will require sidewalk repair and closures within the work zones.
Staples Street – At S Padre Island Drive Intersection (AT&T)
An AT&T contractor is performing a small cell installation along Staples Street, near the intersection of S. Padre Island Drive (SPID), that will require a lane closure on the southbound travel lanes. An additional lane closure on SPID frontage road, for Eastbound direction, is also required for this installation.
Starr Street – North Mesquite Street to North Chaparral Street (Spectrum)
A Spectrum Contractor is performing utility installations along Starr Street, between North Mesquite Street to North Chaparral Street. This work will require sidewalk repair and closures within the work zones. Parking stalls in the work zone will also be closed. Utility installations and sidewalk closures are expected to last one month.
Waldron Road – S Padre Island Drive to Purdue Road (Rock Engineering)
Contractor for the city will be blocking various lanes along Waldron Road for geotechnical drilling operations.
Yorktown Boulevard – Rodd Field Road to Bichon Drive City Project (Grace Paving)
Contractors for the Del Mar Campus have closed the Bay Drive crossover to construct a left-turn bay along eastbound Yorktown Boulevard. Lane closures along this stretch of Yorktown Boulevard is expected to last four months.
ADDITIONAL RESOURCES
"street" - Google News
December 11, 2021 at 05:56AM
https://ift.tt/30lXduo
Street Closures and Traffic Impacts | City of Corpus Christi - Corpus Christi
"street" - Google News
https://ift.tt/2Ql4mmJ
Shoes Man Tutorial
Pos News Update
Meme Update
Korean Entertainment News
Japan News Update
No comments:
Post a Comment